What’s the outlook and timeline for downtown Vernal construction? Vernal City Manager Quinn Bennion reports that both contractors are working diligently to complete the projects before winter weather sets in: Vernal Avenue reconstruction is a UDOT administered and funded project. The contractor will grade and prepare the road subgrade the week of November 4th. Pavement is scheduled for the week of November 11th. Concrete work including the sidewalks will continue through November. The Cobblerock Block project (behind the Main Street buildings) will receive curbing this week and next. Pavement is scheduled for mid-November. Concrete work will continue into early December. Residents are encouraged to shop local and support the businesses in the downtown area who have been disrupted by the construction.